Article 105(Delegation of authority) #
(1) The Minister of Climate, Energy and Environment shall delegate his or her authority falling under the following subparagraphs to the Mayor/Do Governor in accordance with Article 92(1) of the Act: <Amended on Dec. 30, 2009; Dec. 20, 2010; Mar. 23, 2013; Jun. 28, 2016; Dec. 28, 2021; Dec. 12, 2023; Oct. 1, 2025>
1. The following authority concerning national rivers (excluding national rivers falling under subparagraph 2):
a. Receipt of reports pertaining to the succession of rights and obligations pursuant to Article 5(2) of the Act (limited to the matters permitted by the Mayor/Do Governor);
b. Permission for the occupation and use of rivers and publication thereon under Article 33(1)1,5 and 6 of the Act;
c. Vicarious execution of any work that occupies and uses a river under Article 36(1) of the Act and a notice for period of works under Article 36(2) of the Act (limited to the matters permitted by the Mayor/Do Governor);
d. Permission for any act in a flood control area under Article 38 of the Act;
e. Orders issued to restore to the original state, exemption from duties of restoration, the nationalization of installations, etc., the deposit of expenses incurred in relation to the restoration under Article 48 of the Act (limited to the matters permitted by the Mayor/Do Governor);
f. Collection of usage fees related to collection of groundwater pursuant to Article 50(6) of the Act;
g. Refund of erroneously paid charges, etc. under Article 68 of the Act (limited to the payments imposed by the Mayor/Do Governor);
h. Dispositions against violators of statutes issued under Article 69 of the Act (limited to the matters for which the authority concerning permission is delegated to the Mayor/Do Governor);
i. Orders of dispositions or measures under Article 70 of the Act (limited to the matters permitted by the Mayor/Do Governor);
j. Removal, custody, disposition, and other necessary measures, of occupying objects, etc. provided for in Article 73 of the Act;
k. Access, etc. to a third party's land under Article 75 of the Act (limited to the matters for which the authority concerning permission is delegated to the Mayor/Do Governor);
l. Deleted; <Jul. 19, 2016>
m. Reports and entry, etc. under Article 90 of the Act (limited to the matters for which the authority concerning permission is delegated to the Mayor/Do Governor);
n. Hearings under Article 91 of the Act (limited to the matters permitted by the Mayor/Do Governor);
o. Deleted; <Jul. 19, 2016>
p. Imposition and collection of administrative fines under Article 98(3)1,6, and 7 of the Act (limited to the matters for which the authority concerning permission is delegated to the Mayor/Do Governor);
2. The following authority concerning national rivers that belong to any river system of the Anseong River, the Sapgyo River, the Mangyeong River, the Dongjin River, the Tamjin River, the Taehwa River and the Hyeongsan River; provided, the authority under items b through f, p and q regarding river works recognized and publicly notified by the Minister of Climate, Energy and Environment as necessary for river basin management or emergency disaster recovery, etc., shall be excluded:
a. Receipt of reports pertaining to the succession of rights and obligations pursuant to Article 5(2) of the Act (limited to the matters permitted by the Mayor/Do Governor);
b. Formulation and alteration of river works execution plans pursuant to Article 27(1) and (3) of the Act, and the notification thereof;
c. River works under the main clause of Article 27(6) of the Act;
d. River works, and maintenance and repair of rivers, under Article 27(7) of the Act;
e. Notice on the completion of river works pursuant to Article 27(8) of the Act;
f. Consultation with the heads of relevant administrative agencies pursuant to Article 32(3) of the Act (limited to the cases where a river works execution plan has been established or altered, and notified, pursuant to item b);
g. Permission for occupation and use of rivers pursuant to Article 33(1)1,5 and 6 of the Act, and the notification thereof;
h. Execution of works on river occupation and use by proxy under Article 36(1) of the Act and the notice on the period of execution under paragraph (2) of the same Article (limited to the matters permitted by the Mayor/Do Governor);
i. Permission for acts within a flood control area under Article 38 of the Act;
j. Orders for restoration, exemption from the duty to restore, nationalization of installations, etc., and deposit of costs for restoration under Article 48 of the Act (limited to the matters permitted by the Mayor/Do Governor);
k. Collection of usage fees related to collection of groundwater under Article 50(6) of the Act;
l. Refund of erroneously paid charges, etc. under Article 68 of the Act (limited to those imposed by the Mayor/Do Governor);
m. Disposition, etc. against violators of statutes issued under Article 69 of the Act (limited to the matters for which the authority for permission has been delegated to the Mayor/Do Governor);
n. Orders for disposition or taking measures under Article 70 of the Act (limited to the matters permitted by the Mayor/Do Governor);
o. Removal, safekeeping and disposal of occupying objects, etc. and other necessary countermeasures under Article 73 of the Act;
p. Entry, etc. to a third party’s land pursuant to Article 75 of the Act (limited to the matters for which the authority has been delegated to the Mayor/Do Governor);
q. Expropriation and use of land, etc. under Article 78 of the Act (limited to the cases where river works are carried out);
r. Deleted; <Jul. 19, 2016>
s. Report and entry, etc. under Article 90 of the Act (limited to the matters for which the authority for permission has been delegated to the Mayor/Do Governor);
t. Hearings under Article 91 of the Act (limited to the matters permitted by the Mayor/Do Governor);
u. Deleted; <Jul. 19, 2016>
v. Imposition and collection of administrative fines under Article 98(3)1,6, and 7 of the Act (limited to the matters for which the authority has been delegated to the Mayor/Do Governor);
3. In cases of local rivers, the exchange and transfer of a desolate river site, etc. under Article 85 of the Act (limited to the cases where a desolate river site, etc. is national land).
(2) The following authority, from among the authority of the Minister of Climate, Energy and Environment, shall be delegated to the head of a river basin environmental office or the head of a regional environmental office (referring to the head of a river basin environmental office or the head of a regional environmental office who holds jurisdiction over the longest section of a river, in cases falling under subparagraph 1 i and k and subparagraph 3, if a river system is subject to the jurisdiction of at least 2 river basin environmental offices or regional environmental offices, and referring to the a river basin environmental office or the head of a regional environmental office designated by the Minister of Climate, Energy and Environment, in cases falling under subparagraph 2, if a local river is subject to the jurisdiction of at least 2 river basin environmental offices or regional environmental offices) in accordance with Article 92(1) of the Act: <Amended on Dec. 30, 2009; Dec. 20, 2010; Apr. 10, 2012; Mar. 23, 2013; Jun. 28, 2016; Jul. 19, 2016; Jul. 17, 2017; Dec. 28, 2021; Dec. 12, 2023; Oct. 1, 2025>
1. The following authority with respect to national rivers:
a. Receipt of reports on the succession of rights and obligations under Article 5(2) of the Act (limited to the matters permitted or approved by the head of the river basin environmental office or the head of the regional environment office);
b. Consultations or approval under Article 6(1) of the Act (excluding the cases where a project operator is the head of a central administrative agency);
c. Consultations or approval with respect to the establishment of rights and other dispositions under Article 6(2) of the Act (excluding the cases where a project operator is the head of a central administrative agency);
d. Determination, alteration or closure of a river area and the publication thereof under Article 10(1) of the Act;
e. Deleted; <Jun. 28, 2016>
f. Deleted; <Dec. 12, 2023>
g. Designation, alteration, or closure of a flood control area and the publication thereof under Article 12 of the Act;
h. Enactment of management regulations for river facilities under Article 14(1) of the Act and approval for the management regulations for river facilities pursuant to paragraph (2) of that Article;
i. Preparation and keeping of management log books under Article 15(1) of the Act;
j. Conducting examination on riverbed changes under Article 21-2(1) of the Act;
k. Deleted. <Jul. 17, 2017>
l. Formulation and alteration of river works execution plan and the publication thereof under Article 27(1) of the Act;
m. River works of national rivers under the main clause of Article 27(6) of the Act and the maintenance and repair of national rivers under the proviso of that paragraph;
n. River works, and maintenance and repair of rivers, under Article 27(7) of the Act;
o. Notice on the completion of river works pursuant to Article 27(8) of the Act;
p. The implementation of river works by proxy and the publication of the completion of such river works by proxy under Article 28(1) and (2) of the Act;
q. Order to execute works against a person who has caused such works under Article 29 of the Act;
r. Permission for river works and the maintenance and repair of rivers under Article 30(1) of the Act, consultation under paragraph (2) of the said Act and notifications under paragraph (3) of the said Act;
s. Orders issued to deposit the costs of works under Article 30(4) of the Act;
t. Authorization and altered authorization of implementation plans and the publication thereof (excluding implementation plans regarding river waters) under Article 30(5) and (6) of the Act;
u. Authorization of the completion of river works and requests for inspection (limited to the matters for which authority for permission is delegated to the head of the river basin environmental office or the head of the regional environment office) necessary for such authorization under Article 30(7) and (8) of the Act;
v. Comprehensive permission under Article 30(10) of the Act;
w. Consultations with the heads of the relevant administrative agencies under Article 32(3) of the Act;
x. Permission for occupying rivers under subparagraph 2 (excluding multi-purpose dams), subparagraph 3 (excluding multi-purpose dams and river mouth dikes) and subparagraph 4 of Article 33(1) of the Act and authority under paragraphs (5),(6), and (8) of that Article;
y. Implementation of river occupation and use works by proxy and notice on periods of works (limited to the matters permitted by the head of the river basin environmental office or the head of the regional environment office) under Article 36(1) of the Act;
z. Collection of occupation fees, etc. under Article 37(1) of the Act and collection of indemnification under Article 37(3) of the Act;
aa. Prohibition against or restrictions on river use, its publication, and installation of sign boards under Article 47 of the Act;
ab. Orders issued to restore to the original state, exemption from the duty to restore to the original state under Article 48(1) of the Act, notices under paragraph (2) of that Article, the nationalization of installations, etc. under paragraph (3) of that Article, and deposits of expenses for restoration to the original state under paragraph (4) of that Article (limited to the matters for which the authority with respect to permission is delegated to the head of the river basin environmental office or the head of the regional environment office);
ac. Orders to Cities/Dos to bear expenses under Article 61(1) and (2) of the Act;
ad. Refund of erroneously paid charges, etc. under Article 68 of the Act (limited to those imposed by the head of the river basin environmental office or the head of the regional environment office);
(ae) Cancellation of permission or approval under Article 69 of the Act (limited to the matters for which the authority with respect to permission or approval is delegated to the head of the river basin environmental office or the head of the regional environment office);
(af) Orders issued to take dispositions or measures under Article 70(1) of the Act (limited to the matters permitted or approved by the head of the river basin environmental office or the head of the regional environment office) and the notification thereof;
ag. Inspections of the status of river management under Article 74 of the Act;
ah. Entry, etc. into a third party's land under Article 75 of the Act (limited to the matters for which the authority with respect to permission or approval is delegated to the head of the river basin environmental office or the head of the regional environment office);
ai. Expropriation and use of land, etc. under Article 78 of the Act (limited to the cases where river works are carried out);
aj. Purchase, etc. of land under Article 79 of the Act;
ak. Notification and use of desolate river sites, etc. under Article 84 of the Act;
al. Exchange and concession of desolate river sites, etc. under Article 85 of the Act;
ah. Report and entry under Article 90 of the Act (limited to the matters for which the authority with respect to permission or approval is delegated to the head of the river basin environmental office or the head of the regional environment office);
an. Hearing under Article 91 of the Act (limited to the matters permitted or approved by the head of the river basin environmental office or the head of the regional environment office);
ao. Imposition and collection of administrative fines under Article 98(2) of the Act (limited to violations of subparagraph 7 of Article 46 of the Act);
(ap) Imposition and collection of administrative fines under Article 98(3)1,6, and 7 of the Act (limited to the matters for which authority with respect to permission or approval is delegated to the head of the river basin environmental office or the head of the regional environment office);
2. Determination and notification of a management agency or methods for management of rivers under Article 9(2) of the Act and receipt of notification under paragraph (4) of that Article;
3. Formulation, revision and publication of basic river plans provided for in Article 25 of the Act.
(3) The Minister of Climate, Energy and Environment shall delegate the following authority to the head of the competent flood control office in accordance with Article 92(1) of the Act: <Amended on Nov. 16, 2009; Dec. 30, 2009; Dec. 20, 2010; Mar. 23, 2013; Jun. 28, 2016; Jul. 17, 2017; Jun. 8, 2018; Oct. 1, 2025>
1. Receipt of reports on the succession of rights and obligations under Article 5(2) of the Act (limited to the matters permitted by the head of a flood control office);
2. Consultation or approval under Article 6(1) of the Act (limited to the matters for which the authority with respect to permission is delegated to the head of a flood control office, and excluding the cases where a project operator is the head of a central administrative agency);
3. Consultation or approval under Article 6(2) of the Act (limited to the matters for which the authority with respect to permission is delegated to the head of a flood control office, and excluding the cases where a project operator is the head of a central administrative agency);
4. Orders of measures for flood prevention, etc. under Article 14(5) of the Act;
5. Deleted; <Jul. 17, 2017>
6. Deleted; <Jul. 17, 2017>
7. Deleted; <Jul. 17, 2017>
8. Deleted; <Jul. 17, 2017>
9. Deleted; <Jul. 17, 2017>
10. Deleted; <Jul. 17, 2017>
11. Deleted; <Jun. 8, 2017>
12. Deleted; <Jun. 8, 2017>
13. Deleted; <Jun. 8, 2017>
14. Deleted; <Jul. 17, 2017>
15. Requests for submission of records with respect to the management of dams, etc. and flood gates under Article 39(3) of the Act;
16. Deleted; <Jul. 17, 2017>
17. Authority concerning measures for flood control under Article 41 of the Act;
18. Deleted; <Jul. 17, 2017>
19. Deleted; <Jun. 8, 2017>
20. Permission for use of river water under Article 50(1) of the Act, notification under paragraph (2) of that Article, restrictions under paragraph (3) of that Article;
20-2. Reporting on temporary use of river water made under Article 50-2(1) of the Act; limitation, adjustment, and suspension of use, issued under paragraph (2) of that Article; notification made under Article 50(2) of the Act, which shall apply mutatis mutandis under paragraph (3) of that Article;
21. Authority concerning the calculation of the required volume of river water provided for in Article 51 of the Act;
22. Requests for submission of data on the volume of outflow under Article 52(2) of the Act, plans for use of river water and the receipt of records of using river water under paragraph (3) of that Article, and the appraisal of the records of using river water under paragraph (5) of that Article;
23. Authority concerning mediation of the use of river water under Article 53 of the Act;
24. Refund of erroneously paid charges, etc. under Article 68 of the Act (limited to those imposed by the head of a flood control office);
25. Dispositions taken to cancel permission under Article 69 of the Act (limited to the matters for which authority with respect to permission is delegated to the head of a flood control office);
26. Orders of dispositions or measures under Article 70 of the Act (limited to the matters permitted by the head of a flood control office);
27. Entry, etc. into a third party's land under Article 75 of the Act (limited to the matters for which authority with respect to permission is delegated to the head of a flood control office);
27-2. Deleted; <Jul. 17, 2017>
28. Deleted; <Jul. 19, 2016>
29. Authority concerning reports and entry, etc. into a third party’s land under Article 90 of the Act (limited to the matters for which authority with respect to permission or approval is delegated to the head of a flood control office);
30. Hearings held under Article 91 of the Act (limited to the matters permitted by the head of a flood control office);
31. Imposition and collection of administrative fines under Article 98(3)1,6 and 7 of the Act (limited to the matters for which authority with respect to permission is delegated to the head of a flood control office);
32. Imposition and collection of administrative fines under Article 98(3)3 and 5 of the Act.